All Categories
EN
BLOG

BLOG

Home > Blog

Precautions for installation of water pumps above 40kW

Publish time:2025-05-15

When installing a water pump 40kW, the longitudinal and transverse levelness of the base shall not exceed 0.5 ‰. The multistage pump body is centered by the rabbet of each section, and the radial runout and end face runout of the inner and outer circles of the rabbet relative to the axis are not greater than the following table, in millimeters.

The rabbet circular jumping inside and outside the mouththe longitudinal and transverse levelness of the base shall not exceed 0.5 ‰.

The multistage pump body is centered by the stop ports of each section, and the radial runout and end face runout of the inner and outer circles of the stop ports relative to the axis are not greater than the following table, in millimeters.

Stop the circular jumping inside and outside the mouth

pic-1

Rabbet jumping of inner and outer circles

Rabbet diameter≤ 250>250-500>500-800>800-1250>1250-2000
Circular jumping0.0540.060.080.100.02

The roughness of the inner and outer circular mating surfaces of the rabbet  shall not exceed1The pressure for the water pressure test of the pump body is 1.5 times the working pressure, with a duration of 5 minutes and no leakage is allowed.

pic-2

Share